GB hydel project in Gilgit becomes operational after delays
The GB hydel project, a 16-megawatt plant in Gilgit, is running after more than a decade of delays, and the chief minister says it adds eight to nine hours of power.
The 16-megawatt Naltar Phase-III hydropower plant in Gilgit became operational on Sunday, more than a decade behind schedule.
Chief Minister Amjad Hussain says it adds eight to nine hours of power to residents and helps reduce loadshedding.
He has asked Prime Minister Shehbaz Sharif to formally inaugurate the project soon.
Progress stalled at 3 per cent in 2015 and was 72 per cent in 2025 before completion.
The 40-megawatt Hanzel project's tendering will restart within three months.