The GB hydel project in Gilgit, the 16-megawatt Naltar Phase-III hydropower plant, became operational on Sunday, more than a decade behind its original schedule. Gilgit-Baltistan Chief Minister Amjad Hussain announced this during a visit to the facility, where he also pledged to end the region's energy crisis within five years. Hydropower is electricity generated from the force of flowing water, and this plant is one of several such projects planned in the region.
Power supply and the next projects
During the visit, water and power department officials briefed Hussain on electricity supply to Gilgit city. He said the newly launched plant provides eight to nine hours of additional power to residents, which he expects will reduce ongoing loadshedding, the scheduled cuts in supply that households face. He added that he had asked Prime Minister Shehbaz Sharif to formally inaugurate the project soon.
Hussain said wider regional projects remain necessary for a lasting solution. He said the 40-megawatt Hanzel hydropower project has been stalled for seven years and that its tendering process will be started again within the next three months. He also said issues relating to the 54-megawatt Attabad project have been resolved, and that serious efforts are under way to complete the Harpo and Shagarthang hydropower projects.
Why the project ran late
Hussain recalled that the Naltar 14MW Phase-II and 16MW Phase-III projects were included in the federal Public Sector Development Programme (PSDP), a list of state-funded development schemes, in 2009 and launched in 2012. The projects went through three revisions along the way. The progress figures came from the chief minister: work stalled at just 3 per cent by 2015, stayed at 23 per cent through 2024, then accelerated to 72 per cent in 2025 before the plant was completed.
Timeline: what has happened so far
- 2009: Naltar Phase-II and Phase-III are included in the Public Sector Development Programme.
- 2012: The two Naltar projects are launched.
- 2015: Progress on the Phase-III project stalls at 3 per cent.
- 2024: Progress remains at 23 per cent.
- 2025: Progress rises to 72 per cent as work accelerates.
- Sunday: The 16MW Naltar Phase-III plant becomes operational.
Aasan alfaaz mein
Gilgit mein 16 megawatt ka Naltar Phase-III hydropower project ab chalu ho gaya hai, jo ek decade se zyada der se ban raha tha. Chief Minister Amjad Hussain ke mutabiq is se Gilgit shehar ko 8 se 9 ghante ki extra bijli milegi, jis se loadshedding kam hogi. Hanzel project ki tendering dobara teen mahine mein shuru hogi. Aap ke liye matlab yeh hai ke supply behtar ho sakti hai, lekin bills par asar ke baray mein abhi koi wazahat nahi hai.