Ten Balochistan road projects with a combined approved PC-I cost of Rs644.06 billion are scheduled for completion between 2026 and 2028, according to official documents. The schemes sit under the Public Sector Development Programme (PSDP)—the federal development budget—and are meant to strengthen road links, support trade and improve transport across the province.
Three highway projects are due by December 2026, six have deadlines in 2027, and one major scheme is expected to finish in June 2028.
Projects closest to completion
Among the schemes nearest the finish line, the 22.7-kilometre dualisation of Quetta Western Bypass on N-25, costing Rs6.89 billion, has reached 85% physical progress, with Rs6.05 billion already spent. It is scheduled for completion in November 2026.
The 103-kilometre Nokundi-Mashkel road (Rs7.71 billion) is at 79% progress with Rs6.94 billion spent, due in December 2026. The 79.89-kilometre Jhal Jhao-Bela road (Rs16.22 billion) stands at 70% physical progress and Rs13.87 billion spent, also due in December 2026.
N-25 corridor and larger schemes
Substantial investment is concentrated on N-25, the corridor linking Karachi, Quetta and Chaman. The 330.52-kilometre Khuzdar-Kuchlak section (Rs98.90 billion) is at 61% physical progress with Rs42.86 billion spent by September 2026, due in December 2027.
The 273-kilometre Karachi-Kararo and Wadh-Khuzdar section (Rs183.42 billion) has spent Rs36.53 billion but is only 19% complete, targeting December 2027. The 187-kilometre Kararo-Wadh and Kuchlak-Chaman section (Rs132.75 billion) has spent Rs30.07 billion at 22% progress, also due in December 2027.
On M-8, the 168-kilometre Awaran-Naal section (Rs32.24 billion) is at 52% progress with Rs20.45 billion spent, due in June 2027. The 146-kilometre Hoshab-Awaran road (Rs25.84 billion) is at 64% progress with Rs9.75 billion spent, also due in June 2027.
N-50 stretches still early
Dualisation and improvement of N-50 from Yarik-Sagu to Zhob, including the Zhob Bypass (Rs76.49 billion), is only 2% complete with Rs975 million spent, scheduled for November 2027. Looking to 2028, the 305-kilometre Kuchlak-Zhob section of N-50 (Rs63.60 billion) is at 16% physical progress with Rs11.71 billion spent by September 2026, due in June 2028.